| American Recovery & Reinvestment Act (ARRA) - Public Works
PROJECTS | DESCRIPTION | AMOUNT ALLOCATED | STATUS | Landscape Enhancement | Jeffrey/I-405 Bicycle Bridge Landscaping Enhancement Project | $354,000 | Completed | Rehabilitation | Red Hill Rehabilitation Project | $2,456,000 | Completed |
Transportation
Jeffrey/I-405 Bicycle Bridge Landscaping Enhancement Project
| Location: | Citywide | Allocation: | $354,000 | Funds Expended: | $344,109 | Status: | Completed | Start Date: | February 2010 | End Date: | July 2010 (Construction) - August 2011 (Plant establishment) | | Jobs Created: | 0 | | Description: | Plant new trees and shrubs, install mulch, install new reclaimed water meter and service lateral, flow sensor, master valve, mainline and lateral lines, spray heads, control wire, upgrade existing controller, install new controller and pedestal meter, and furnish and install interpretive signs as specified in the Special Provisions. |
Red Hill Rehabilitation Project
| Location: | Red Hill Avenue between Reynolds Avenue and Deere Avenue | Allocation: | $2,456,000 | Funds Expended: | $1,954,192.84 (construction) | Status: | Construction Complete | Start Date: | January 2010 | End Date: | May 2010 | Jobs Created: | 0 | Description: | Pavement rehabilitation work to be performed on Red Hill Avenue between Reynolds and Deere shall include, but not be limited to: Cold milling; removal and replacement of AC pavement; AC and ARHM pavement surface course overlay; adjusting valve covers to grade; removal and replacement of damaged concrete curb, gutter and sidewalk; modifying curb ramps; installation of video detection; and other items not mentioned here, but are required by the plans and the Special Provisions. | <><><> > |
| |